  • Abdulazizov Doniyor Nazrullaevich Project Management Consultant Author

Keywords:

public investment management; World Bank; Investment Project Financing; Program-for-Results; institutional frictions; project governance; transaction costs; risk management; Uzbekistan

Abstract

This study examines why governance arrangements do not always translate into timely decisions and development results in the World Bank-financed public investment operations. Using comparative qualitative case analysis, documentary analysis, and process tracing, it investigates two Investment Project Financing operations and one Program-for-Results operation in Uzbekistan; five additional operations provide triangulation. The unit of analysis is the management process rather than the project. Evidence identifies an agreement-to-implementation gap: legal agreements, appraisal documents, operational manuals, and national acts establish legitimate requirements, yet their combination can create duplicated controls, responsibility without decision rights, fragmented data ownership, and delayed escalation. IPF and PforR require different management architectures. IPF depends on integration across scope, procurement, contracts, expenditure, and outputs, whereas PforR depends on a result-delivery chain linking program ownership, administrative data, evidence, and independent verification. The article proposes a differentiated Institutional Risk Governance Framework comprising an alignment gate, decision-rights mapping, a control-value test, interface-risk management, an Individual Comments Map, and a Process and Risk Ledger. The contribution lies not in inventing these generic tools, but in integrating them around documented institutionalization gaps in World Bank operations in Uzbekistan. The framework is a design proposition requiring prospective pilot validation.

References

1.Aris, Stephen, and Michael Hubbard. 2015. Can donor project implementation units support country systems? Development Policy Review 33: 759–781. https://doi.org/10.1111/dpr.12133.

2.Beach, Derek, and Rasmus Brun Pedersen. 2019. Process-Tracing Methods: Foundations and Guidelines. 2nd ed. Ann Arbor: University of Michigan Press.

3.Brannick, Teresa, and David Coghlan. 2007. In defense of being “native”: The case for insider academic research. Organizational Research Methods 10: 59–74. https://doi.org/10.1177/1094428106289253.

4.Calvo, Eduard, Ruomeng Cui, and Juan Camilo Serpa. 2019. Oversight and efficiency in public projects: A regression discontinuity analysis. Management Science 65: 5651–5675. https://doi.org/10.1287/mnsc.2018.3202.

5.Clist, Paul. 2016. Payment by results in development aid: All that glitters is not gold. World Bank Research Observer 31: 290–319. https://doi.org/10.1093/wbro/lkw005.

6.Clist, Paul. 2019. Payment by results in international development: Evidence from the first decade. Development Policy Review 37: 719–734. https://doi.org/10.1111/dpr.12405.

7.Cormier, Ben. 2016. Empowered borrowers? Tracking the World Bank’s Program-for-Results. Third World Quarterly 37: 209–226. https://doi.org/10.1080/01436597.2015.1108828.

8.Dávid-Barrett, Elizabeth, Mihály Fazekas, Olli Hellmann, Lili Márk, and Ciara McCorley. 2020. Controlling corruption in development aid: New evidence from contract-level data. Studies in Comparative International Development 55: 481–515. https://doi.org/10.1007/s12116-020-09315-4.

9.Denizer, Cevdet, Daniel Kaufmann, and Aart Kraay. 2013. Good countries or good projects? Macro and micro correlates of World Bank project performance. Journal of Development Economics 105: 288–302. https://doi.org/10.1016/j.jdeveco.2013.06.003.

10.Eisenhardt, Kathleen M. 1989. Building theories from case study research. Academy of Management Review 14: 532–550. https://doi.org/10.5465/amr.1989.4308385.

11.El Baradei, Laila. 2011. Parallel structures in the Egyptian government bureaucracy: A problematic quick fix. Public Administration 89: 1351–1366. https://doi.org/10.1111/j.1467-9299.2011.01941.x.

12.Gelb, Alan, and Nabil Hashmi. 2014. The anatomy of Program-for-Results: An approach to results-based aid. Center for Global Development Working Paper. https://doi.org/10.2139/ssrn.2466657.

13.George, Alexander L., and Andrew Bennett. 2005. Case Studies and Theory Development in the Social Sciences. Cambridge, MA: MIT Press.

14.Government of Uzbekistan. 2018. Presidential Resolution No. PP-3857 of 16 July 2018, “On Measures to Improve the Effectiveness of Preparation and Implementation of Projects with the Participation of International Financial Institutions and Foreign Governmental Financial Organizations”. Tashkent.

15.Government of Uzbekistan. 2021. Law No. ZRU-684 of 22 April 2021, “On Public Procurement”, as amended. Tashkent.

16.Government of Uzbekistan. 2025. Presidential Resolution No. PP-51 of 11 February 2025, “On Additional Measures to Improve the Mechanisms for Preparation and Implementation of Projects with the Participation of International Financial Institutions and Foreign Governmental Financial Organizations”. Tashkent. https://lex.uz/docs/7374216.

17.Heinzel, Mirko, and Andrea Liese. 2021. Managing performance and winning trust: How World Bank staff shape recipient performance. Review of International Organizations 16: 625–653. https://doi.org/10.1007/s11558-021-09414-4.

18.Independent Evaluation Group. 2016. Program-for-Results: An Early-Stage Assessment of the Process and Effects of a New Lending Instrument. Washington, DC: World Bank. https://ieg.worldbankgroup.org/evaluations/program-for-results.

19.International Bank for Reconstruction and Development. 2025. Loan Agreement No. 9901-UZ: EduImkon: Redesigning Opportunity, Delivering Education Equity Program. Washington, DC: World Bank.

20.International Development Association. 2019. Financing Agreement, Credit No. 6446-UZ: Uzbekistan Strengthening Social Protection System Project. Washington, DC: World Bank.

21.International Development Association. 2022. Financing Agreement, Credit No. 7138-UZ: Uzbekistan Resilient Landscapes Restoration Project. Washington, DC: World Bank.

22.International Organization for Standardization. 2018. ISO 31000:2018 Risk Management—Guidelines. Geneva: ISO.

23.International Organization for Standardization. 2020. ISO 21502:2020 Project, Programme and Portfolio Management—Guidance on Project Management. Geneva: ISO.

24.Jensen, Michael C., and William H. Meckling. 1976. Theory of the firm: Managerial behavior, agency costs and ownership structure. Journal of Financial Economics 3: 305–360. https://doi.org/10.1016/0304-405X(76)90026-X.

25.Knack, Stephen. 2013. Building or bypassing recipient country systems: Are donors defying the Paris Declaration? Journal of Development Studies 50: 839–854. https://doi.org/10.1080/00220388.2014.895816.

Downloads

Published

2026-10-05